EXCAVATION PIT CONSTRUCTION SITUATION BYPASS | beuren

.

Services MSIng

Technical processing (statics plans) of theexcavation lining.

Two different installation types were usedMission. In the case of great height and neighboring buildings, double back-anchored reinforced concrete bored piles with shotcrete infill and mounted fall protection were designed. Otherwise, a Berlin shoring was ordered.

builder

Kirchheim Road Construction Office

client
Fichtner Bauconsulting GmbH | Stuttgart