Planning and technical processing of the complex renovation of the Cone 6. Planning/manufacturing steps: erection and first jacking up of the supporting framework, demolition of the east wall with high-pressure water jet and small pneumatic hammer for the profiling, second jacking up of the supporting framework, production of the reinforcement (special features: reinforcement welding, boreholes l = 2.5 m along the 30 mm shell for hanging back with Gewi rods), production of the formwork, concreting with SCC in a "closed cavity", strengthening of the south-west wall with an inner facing wall, lowering and dismantling of the shoring, strengthening of the contaminated construction joint through dismantling/new construction using the pilgrimage method.